    Will the Tampere tram be extended to Pirkkala and Linnainmaa?

    Plans for new tram lines in the Tampere region.

    Answered at: Checked at:

    Short answer

    The City of Tampere says the decision to build the Pirkkala–Linnainmaa tramway was made in 2024 and construction reached its halfway point in June 2026, ahead of schedule. Phase 1 runs from Sorin aukio to Partola and from Kaupin kampus to Ruotula, with temporary end stops, and service is targeted for August 2028. Phase 2, from Sorin aukio to Suuppa (about 9.3 km) and from Kaupin kampus to Linnainmaa (4.3 km), needs state funding to be confirmed, and service could begin in early 2032. A project plan for a Lielahti–Ylöjärvi line is due in spring 2027.

    Transport, roads, car rental

    Why

    1. Phase 1 to Partola and Ruotula: August 2028.
    2. Phase 2 to Suuppa and Linnainmaa: possibly early 2032.
    3. Phase 2 needs confirmed state funding.

    Details

    Nysse's draft route network for August 2028 has tram line 3 running from Hervantajärvi via Hatanpää to Härmälä and Partola.

    Tip

    If you live near the new lines, follow Nysse's 2028 route plan, as bus lines will change too.

    What may differ

    Nysse says final decisions on the 2028 route network will be made at the end of 2026.

    Common misconception

    The Tampere tram network is already finished.

    What actually happens

    New lines to Partola and Ruotula are due in August 2028.

    People also ask

    • How many people use the Tampere tram?
    • What tram lines run in Tampere?
    • Will Tampere bus routes change in 2028?

    Sources

    This answer is for reference only. Local ticket prices and routes change, so check the local public transport website before you travel.

    Transport, roads, car rental